A new 5″ circuit with passing loop is to be constructed in addition to the existing raised circuit.

For pictures see the Newsletter

 

June 2019

The trackbed has now been ballasted from the station down and through the green tunnel.

A large number of track panels have been constructed and are awaiting installation.

May 2019

The creation of a 5 inch ground level line is well under way. A lot of the track bed has been excavated and ballasted and track laying has commenced.

The Wednesday morning working party would welcome anyone interested in helping.